OneTripDIY
Concrete Footing Calculator — How Much Concrete for a Footing?

Concrete Footing Calculator — Volume, Bags and Rebar

A footing is a long box of concrete under a wall. The arithmetic is simple; what catches people out is that a trench is never the size they dug it, and the bags run out at 80% done.

ft

Add up every run. For a rectangle it is the perimeter.

in.

Usually twice the wall thickness. 16 in. suits an 8 in. block wall.

in.

The thickness of the concrete, not how deep the trench is dug.

bars

Continuous bars running the length. Two is typical for a 16 in. footing.

%

Trench walls slump and the bottom is never flat. 8% is realistic, 15% in loose soil.

Bigger bags are cheaper per cubic foot and there are fewer to open.

Concrete needed cu yd
In cubic feet cu ft
Or in bags bags
Which way to buy
Rebar × 20 ft lengths
Footing footprint sq ft

Estimates only. Check against your supplier's stated coverage before you buy.

Take this list to the store

We'll email the quantities above, what you typed in, and a link that reopens this calculator already filled in — so you can adjust it on your phone in the aisle.

We send the list you asked for. Anything else only if you tick the box, and you can unsubscribe in one click. What we do with it.

A footing is a long boxLength times width times depth, converted to cubic yards.A footing is a long box of concreteLengthWidthDepth÷ 27 for yardscubic yards1.33Cubic feet divided by 27. Order the next round number up.

How to work it out

  1. Find out how deep your frost line is

    A footing has to bear on undisturbed soil below the frost line, or the ground will lift it in winter and drop it in spring. That depth is local — a few inches in the south, four feet or more in the northern states — and your building department publishes it.

    This is not a number to estimate. Call and ask before you dig, because it changes how much you excavate and often whether you need an inspection before you pour.

  2. Measure the footing, not the trench

    The width and depth to enter are the finished dimensions of the concrete. The trench is deeper than the footing is thick — the rest of that depth is backfill or the wall that sits on top.

    A common footing under an 8 inch block wall is 16 inches wide and 8 inches thick, sitting at the bottom of a trench that might be 40 inches deep.

  3. Add for the over-dig

    No trench comes out the size you meant. The sides slump, the bottom is uneven, and the first thing concrete does is find every low spot. Forming the sides with lumber gives you exact dimensions and is worth it on a small job; trenching straight into firm soil is faster and needs an allowance.

    Eight per cent is honest for firm ground. In sand, loose fill or anything that crumbles, use 15% — and form it if you can.

  4. Check the total before you decide how to buy

    Above about a cubic yard, bags stop making sense. A cubic yard is forty-five 80 lb bags — well over a ton of material to carry, open, mix and place before the first batch starts setting.

    Ready-mix comes on a truck, arrives in one pour with no cold joints, and usually costs less per yard than the equivalent in bags. Most suppliers have a minimum load and a short-load fee; ask what theirs is before you decide.

Concrete per linear foot of footing

Cubic feet for one foot of length, before any over-dig allowance.

Width6 in. thick8 in. thick10 in. thick12 in. thick
12 in.0.500.670.831.00
16 in.0.670.891.111.33
18 in.0.751.001.251.50
20 in.0.831.111.391.67
24 in.1.001.331.672.00

Multiply by your total length, then divide by 27 for cubic yards or by 0.60 for 80 lb bags.

Bags versus ready-mix

What a given volume costs you in effort.

Volume80 lb bags60 lb bagsSensible choice
10 cu ft1723Bags, comfortably
20 cu ft3445Bags, but it is a long day
27 cu ft (1 cu yd)4560Borderline — price ready-mix
40 cu ft6789Ready-mix
54 cu ft (2 cu yd)90120Ready-mix, no question

An 80 lb bag yields 0.60 cu ft. Mixing more than about 30 bags by hand in one session is genuinely hard work.

How much concrete for a 40 foot footing?

Forty feet of footing at 16 inches wide and 8 inches thick is 40 × 1.33 × 0.67 = 35.6 cubic feet. With an 8% over-dig allowance that becomes 38.4 cu ft, which is 1.42 cubic yards.

In 80 lb bags that is 64 bags — more than a ton, and a full day of mixing. At that volume ready-mix is both cheaper and faster; order 1.5 cubic yards and ask about the short-load fee.

Two continuous rebar runs over 40 feet, with an 8% allowance for lapping at the splices, is 86 linear feet, which is five 20 ft bars.

How wide and how thick should a footing be?

The traditional rule is that a footing is twice the width of the wall it carries and at least as thick as the wall, projecting equally on both sides. An 8 inch block wall therefore gets a 16 inch wide footing, at least 8 inches thick, with 4 inches of projection each side.

That rule is a starting point, not the answer. The real requirement depends on what the wall carries and what the soil underneath can bear — the IRC has prescriptive tables, and anything unusual wants an engineer. Soft clay, fill, or a high water table all change the answer, sometimes dramatically.

Minimum thickness in the code is generally 6 inches. Going deeper than 8 inches on a residential footing rarely helps; going wider is what spreads the load.

Why footings fail, and it is almost never the concrete

Footings crack and settle for three reasons, and the concrete mix is rarely one of them.

Frost heave. The footing was not below the frost line. Water in the soil freezes, expands, lifts the footing, and drops it unevenly in spring. This is the most common cause of a cracked foundation wall in cold climates.

Disturbed soil. The trench was dug too deep and backfilled to level, or dug in fill that was never compacted. Concrete poured on loose soil settles into it. If you overdig, fill the extra depth with compacted gravel, never loose dirt.

Water. Poor drainage against the footing softens the bearing soil over years. A perforated drain pipe in gravel alongside the footing, running to daylight, costs very little at the time and solves it permanently.

Rebar: how much and where it goes

Rebar in a footing resists the bending that happens when the soil underneath is not perfectly uniform. Two continuous #4 bars — half inch — running the length is standard for a residential strip footing. Wider footings take three or four.

Position matters as much as quantity. The bars sit in the lower third of the pour, about 3 inches up from the bottom and 3 inches in from each side, held there on plastic or concrete chairs. Bars laid on the dirt and left there do nothing at all: concrete has to surround them completely or they rust and split the footing from the inside.

Splices lap rather than butt. The usual figure is 40 bar diameters, so 20 inches for a #4 bar, wired together. That is where the 8% the calculator adds goes.

At corners, bend a bar round or add an L-shaped piece lapping into both runs. A corner where two straight bars simply stop is the weakest point in the whole footing.

Stepped footings on a slope

On sloping ground a footing does not follow the slope — it steps. Each level run sits flat, then the footing steps up or down to the next level, with a vertical face between them.

The code limits how steep those steps can be: generally the vertical step is no more than three quarters of the horizontal run between steps, and no step is taller than the footing is thick without extra reinforcement.

For the volume, treat each level run as a separate footing and add them, then add the vertical steps as small blocks. The calculator handles this if you total the lengths and pour the steps as part of the same order — just add a little more than 8%, because stepped footings need formwork and formwork leaks.

Pouring: what to have ready before the truck arrives

A ready-mix truck gives you a limited window before it starts charging waiting time, and concrete does not pause. Everything has to be ready first.

The trench inspected if your area requires it. Rebar tied and chaired. Forms braced — concrete is far heavier than people expect and an unbraced form will bow or burst. A route for the truck, or a plan for barrowing, with boards down over soft ground. Enough people: pouring 1.5 yards is not a one-person job.

Screed the top roughly level but do not trowel it smooth. A footing wants a slightly rough surface for the wall above to key into, and many block walls need a keyway formed down the middle while the concrete is still wet.

How this is worked out

No black box — here is the arithmetic the calculator runs, so you can check it against your own numbers.

  1. volume = length × width ÷ 12 × depth ÷ 12 Length in feet, width and depth in inches, giving cubic feet.
  2. × (1 + over-dig ÷ 100) 8% for firm soil, 15% for anything loose or unformed.
  3. cubic yards = cubic feet ÷ 27 A cubic yard is 3 × 3 × 3 feet.
  4. bags = cubic feet ÷ bag yield 80 lb = 0.60 cu ft; 60 lb = 0.45; 50 lb = 0.375; 40 lb = 0.30.
  5. rebar = length × bars × 1.08 Continuous runs, plus 8% for the lap at every splice.
  6. lengths = rebar feet ÷ 20, rounded up Rebar is commonly sold in 20 ft sticks.

Common questions

How much concrete do I need for a footing?

Length in feet times width in inches divided by 12, times depth in inches divided by 12. A 40 ft footing at 16 by 8 inches is 35.6 cubic feet, or about 1.4 cubic yards once you allow for over-dig.

How deep does a footing need to be?

Below your local frost line, which varies from a few inches in the south to over four feet in the north. Your building department publishes the figure — ask, because it is not something to estimate. The concrete itself is usually 8 inches thick; the trench is much deeper.

How wide should a footing be?

The rule of thumb is twice the width of the wall above, projecting equally each side. An 8 in. block wall gets a 16 in. footing. Soil bearing capacity and load can change that, so check the IRC tables or ask an engineer for anything unusual.

Do I need rebar in a footing?

Almost always, and many jurisdictions require it. Two continuous #4 bars is standard for a residential strip footing. They have to sit up off the bottom on chairs with concrete all around them — bars lying on the dirt do nothing.

How many bags of concrete are in a cubic yard?

Forty-five 80 lb bags, sixty 60 lb bags, or ninety 40 lb bags. That is over a ton of material either way, which is why a cubic yard is roughly where ready-mix becomes the better answer.

Can I pour a footing in cold weather?

With precautions. Concrete needs to stay above freezing while it cures, and pouring onto frozen ground is not acceptable at all — it thaws later and the footing drops. Insulating blankets, heated water in the mix and accelerators all help, but if the ground is frozen, wait.

What if my trench is wider than I planned?

You pour the extra concrete, because it will find every inch. That is what the over-dig allowance covers. If a section is badly over-dug, fill the excess with compacted gravel rather than concrete — but never with loose soil, which settles under the load.

How long before I can build on a footing?

Typically 24 to 48 hours before laying block, and about a week before any significant load. Concrete reaches most of its design strength at 28 days, but a footing only needs to carry the wall going up on it, which is a fraction of that.

Where these figures come from

Every figure below is traceable. How we check the numbers explains how they are verified, and the coverage reference collects them all in one place.

  • International Residential Code, section R403 (footings) — minimum thickness, width and frost depth requirements
  • American Concrete Institute ACI 318 — rebar cover, lap length and placement
  • Bagged concrete manufacturer yield data — cubic feet per bag by weight

Think a number here is wrong? Tell us — we check every report, correct the page, and date the change. Last checked September 12, 2026.